PAKISTAN

Since October 2012, WMI experts are working in Pakistan on the Project “Extension of water resources for Faisalabad City – Phase 1” for the improvement of Water Supply. Link to the reference sheet

Regarding the activity of leak detection on the network, WMI chose Helium gas tracking method as the pressure in the network is too low to generate any leakage sound detectable by classic acoustic devices. Thanks to this method, 300 km of linear have been audited already and 250 leaks localized to date.

The consumption of both domestic and large customers is currently studying. More than 300 consumption profiles have been established to date.

Pressure regulation valves, bulk meters and the SCADA system have all been received on site and the installation is about to begin.

 
METERING AND BUSINESS MANAGEMENT
One problem that water-system managers must solve and/or prevent from recurring is inadequate metering. To help prevent under-reporting of water use, WMI provides technical solutions along with a water meter-renewal policy that features diagnostics and...
REDUCTION OF THE PHYSICAL WATER LOSSES OF THE WATER DISTRIBUTION NETWORK OF CASABLANCA
Reduce as much as possible the physical water losses in the critical water supplying area (WSA) of Casablanca city (supplying time 24h/24h), Lydec, delegated authority operating on the network with the aim of reaching as soon as possible an overall network efficiency of 85%.